NYANYADZI IRRIGATION PROJECT
Nyanyadzi Irrigation Project is in Manicaland Province and was awarded to Conardic Investments (Pvt) Ltd in 2019. It is one of the Irrigation Schemes which were picked by the Government of Zimbabwe for Rehabilitation after a number of Zimbabwe’s Irrigation Schemes were damaged by Cyclone Idai in the 2018-2019 rain season.
Its scope of works included the:
- Supply, delivery and rehabilitation of a 3km x 500mm mPvc and Steel pipe network.
- Construction of Anchors and Thrust blocks to support the water pipes since they pass through various bends and gulleys,
- Servicing of 2 X Kirloskar Vertical Turbine pumps as well as
- Desiltation of its Weir where around 4000m3 of silt were removed from the weir
- CLIENT NYANYADZI
- YEAR 2018
- WE DID IRRIGATION PROJECT
- TAGS Agro-Construction , All borehole & irrigAtion equipment & services , All building mAteRIAls , All pvc & cAst iron fittings-gAte VAlves , bends , culvert pipes , electricity poles , kerb stones , lintels , mAnhole cover slAbs & lids , mAnhole rings , municiPAl kerbs , PAVIng , PAVIng slAbs , plumbing , porous pipes , short collAr joints , VAlve boxes & lids